Westenergy Waste Incineration Plant

Construction of a new waste incineration plant in Mustasaari.

Size

16.000 m2

Location

Mustasaari

Contract

Shared contract

Sum

7,01 meur

Duration

12 months

Ready

2012

Subscriber

Westenergy Oy

Construction of a new waste incineration plant by Westenergy in Mustasaari.

The Westenergy incinerator building is 160 metres long and 32 metres high. The height of the stack is 75 metres.

The plant has a surface area of 16,000 m2 and the foundations have been poured with approximately 19,000 m3 of concrete.

The steel work for the power plant was carried out by WasaCon Oy, for whom WasaSteel Oy was responsible for the steel supply. The delivery included steel structures for the facade, facade panels, doors, windows, roofs, etc.

Cookie settings

This website uses cookies to provide you with the best possible user experience. Cookies are stored in your browser and help us to recognise you when you return to the website. They also help our team to understand which parts of the website are interesting and useful to you.

Necessary cookies

In order to save your cookie settings, the necessary cookies must be enabled.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site and the most popular pages.

Keeping this cookie enabled helps us to improve our website.